Assistance to the Infrastructure Contracting Authority

TechnicAtome provides support for the Defence Infrastructure Service (SID) in the naval bases of Toulon and Brest, to adapt reception and support facilities for nuclear submarines.

TechnicAtome provides support for SID to develop a master plan and prepare the infrastructure transformation programmes of the naval bases in Toulon and Brest.This assistance mission features a special dimension relating to nuclear safety.   

Main stages for Toulon:

  • 2015 : Drawing up the 1st master plan of the port area comprising the 3 docks for berthing SNA BARRACUDA.
  • 2016-2017 : The adjustment programme for the 2nd dock (2017-2023).
  • 2017-2018 : The adjustment programme for the 3rd dock (2017-2027).
  • 2019 : Using a PLM to control the configuration.
  • 2019 and after: Supervision of the design and production of adjustments to the 2nd and 3rd docks.
  • Late 2020: start of work on dock 2.